City Springs Construction Contract Dispute Resolved

July 20, 2021

At the close of construction of the City of Sandy Springs $239 million City Springs project, a dispute arose between Holder Construction Group and the City of Sandy Springs Public Facilities Authority regarding payments due under the contract. The dispute and related construction questions have been resolved. Both parties have agreed to dismiss all claims; the Authority will pay $1,800,000 to Holder, concluding the contract between the parties. The Authority's civil action against the Rosser architectural firm is awaiting a decision from Fulton County Superior Court.